Entry for Jobs Completed; Cost of Unfinished Jobs The following account appears in the ledger prior to recognizing the jobs completed in January: Work in

Entry for Jobs Completed; Cost of Unfinished Jobs

The following account appears in the ledger prior to recognizing the jobs completed in January:

Work in Process
Balance, January 1 $11,190
Direct materials 90,970
Direct labor 98,140
Factory overhead 51,590

Jobs finished during January are summarized as follows:

Job 210 $45,340 Job 224 $52,900
Job 216 27,710 Job 230 95,720

Question Content Area

a. Journalize the entry to record the jobs completed. If an amount box does not require an entry, leave it blank.

Question Content Area

b. Determine the cost of the unfinished jobs at January 31. $fill in the blank 3942baff9ff4fbb_1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions