EOQ Ross White's machine shop uses 2 5 0 0 brackets during the course of a Qear, and this usage is relatively constant throughout the

EOQ
Ross White's machine shop uses 2500 brackets during the course of a
Qear, and this usage is relatively constant throughout the year. These
brackets are purchased from a supplier 100 miles away for $15 each,
and the lead time is 2 days. The holding cost per bracket per year is
$1.50(or 10% of the unit cost) and the ordering cost per order is
$18.75. There are 300 working days per year.
a. Develop a total cost model for this system.
b. What is the EOQ for this problem?
c. What is the cycle time?
d. What is the reorder policy?
e. What are the total annual holding and ordering costs associated
with your recommended EOQ ?
f. What is the total annual cost associated with your recommended
EOQ?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Today

Authors: Terri A. Scandura, Kim Gower

1st Edition

1506385877, 978-1506385877

More Books

Students also viewed these General Management questions