er uses machine hours to allocate overhead cost to products. Budgeted information for the current year follows. Budgeted overhead cost $ 54,400 Budgeted machine hours
er uses machine hours to allocate overhead cost to products. Budgeted information for the current year follows.
Budgeted overhead cost | $ 54,400 | |
---|---|---|
Budgeted machine hours | 640 | machine hours |
(a) Compute the plantwide overhead rate based on machine hours. (b) How much overhead cost is allocated to Job A2, which uses 4 machine hours?