Answered step by step
Verified Expert Solution
Question
1 Approved Answer
es 10 Question 17 n Completion Status: Activity A B C D E ANSWERS: MA Duration 7 2 6 7 5 6. What is
es 10 Question 17 n Completion Status: Activity A B C D E ANSWERS: MA Duration 7 2 6 7 5 6. What is the total cost for activity A 7. What is the total cost for activity C 8. What is the total cost for activity E n Precedence ww B B nds. QUESTIONS: 1. What is the duration of this project if executed without resource levelling? 2. What is the critical path for this project? (only write the number, no spaces, i.e. "ABCD") 3. What is the total resource needed to complete this project? S 4. If the labour histogram is drawn without any resource levelling, what would the peak resource need be? 5. During which week/weeks will the peak resource need be? (if there is only on week just write the week i.e. "1". If there are more than one weeks, only the week and a comma in between. i.e. "1,2". Resource Requirement per week hp 1 a 3 5 2 2 32 points 16C ^4) ENG 14:09 2021/09/01 Save Answer
Step by Step Solution
There are 3 Steps involved in it
Step: 1
What is the duration of this project if executed without resource levelling The duration of the project is 7 weeks Resource levelling is a process of ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started