Estimate the levelized cost of electricity for a 3-MW wind turbine, given the following facts: Total capital investment of 6 million USD Annual operating costs
Estimate the levelized cost of electricity for a 3-MW wind turbine, given the following facts: Total capital investment of 6 million USD Annual operating costs of 10 USD/MWh Capacity factor of 40 % (percentage of time turbine actually produces power) WACC of 8 % Economic life of 20 years Assume the turbine is purchased and erected in year 0 and begins producing power in year 1.