Question

1 Approved Answer

Estimate the total direct cost and cost per 1,000 bf of lumber for transporting 70,000 bf of lumber from the lumberyard to a jobsite, which

Estimate the total direct cost and cost per 1,000 bf of lumber for transporting 70,000 bf of lumber from the lumberyard to a jobsite, which is 18 miles from the yard. Each truck can haul 3,000 bf per load and can average 40 mi/hr loaded and 45 mi/hr empty. Assume $55.00/hr for a truck with a driver.

Two laborers will load lumber onto the trick at the yard and another 2 laborers will unload the truck and stack the lumber at the job. Each laborer can handle 1,200 bf/hr. Assume laborers cost $21.00/hr. Assume a 50-min effective hour and determine the cost per 1,000 bf of lumber based on using the economical number of trucks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing With The Computer

Authors: Wayne S. Boutell

1st Edition

0520363329, 978-0520363328

More Books

Students also viewed these Accounting questions