Question
Estimated value = 0.6*$50,000 = $30,000 Planned Value = 0.8*$50,000 = $40,000 Actual Cost = $45,000 The Cost Performance Index = 30,000/45,000 = .667 Overbudget
Estimated value = 0.6*$50,000 = $30,000
Planned Value = 0.8*$50,000 = $40,000
Actual Cost = $45,000
The Cost Performance Index = 30,000/45,000 = .667 Overbudget
Schedule Performance Index = 30,000/40,000 = .75 Behind
Budget at Completion Value = $50,000
EAC with SPI and CPI factors = 45,000 + 50,000 - 30,000= $65,000
ETC = 50,000 / 0.66 - 45000 = 75757 - 45000 = $31000
I have a few more I needed answers to:
1) Using the above calculated EV, AC,BAC, CPI, and SPI calculate the estimate at completion value for estimated to complete work considering both SPI and CPI factors: EAC =
2)Using the above calculated EV, AC, BAC, and EAC for exercise G, calculate the To-complete performance index (based on EAC)
3) Using the above calculated EV, AC, and BAC calculate the To-Complete Performance Index (Based on the BAC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started