ET459 Class exercise 2: find the critical path and duration of the following project.
\table[[Activity,Predecessors,Normal Duration (weeks)],[A,-,6],[B,A,10],[C,A,8],[D,B,12],[E,B,C,10],[F,C,14],[G,D, C,7],[H,E,F,9],[I,G,H,6],[J,I,5],[K,I,6],[L,J, K,8],[M,I, K,8],[N,J, K,6],[O,L, M, N,7],[P,O,6]]