Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

EVM Indicator Week 1 Week 2 Week 3 Formula used Cost Variance $2,000 $6,000 $9,200 Cost Variance = Earned Value - Actual Cost Schedule Variance

EVM Indicator Week 1 Week 2 Week 3 Formula used Cost Variance $2,000 $6,000 $9,200 Cost Variance = Earned Value - Actual Cost Schedule Variance -$4,750 $0 $4,000 Schedule Variance = Earned Value - Planned Value Cost Performance Index 1.4 1.375 1.243 Cost Performance Index = Earned Value / Actual Cost Schedule Performance Index 0.596 1.0 1.093 Schedule Performance Index = Earned Value / Planned Value Estimated Cost at Completion (use the EAC - BAC / CPI formula) $37, 321.43 $38,000 $42,022.34 Estimated Cost at Completion = Budget at Completion / Cost Performance Index Estimated Cost to Complete $32, 321.43 $22,000 $4,222.34 Estimated Cost to Complete = Estimated Cost at Completion - Actual Cost

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective Project Management Traditional Agile Extreme

Authors: Robert K. Wysocki

7th Edition

1118729161, 978-1118729168

More Books

Students also viewed these General Management questions

Question

What two sets of parameters must be estimated in time-driven ABC?

Answered: 1 week ago

Question

=+What kind of question would you ask to encourage their response?

Answered: 1 week ago

Question

=+Does it keep the visitor reading?

Answered: 1 week ago