Question

1 Approved Answer

EVM Question January feb mar april may june july plan %comp value Activity staffing 8 7 15 100 - blueprinting 4 6 10 80 -

EVM Question January feb mar april may june july plan %comp value

Activity

staffing 8 7 15 100 -

blueprinting 4 6 10 80 -

Prototype development 2 8 10 60 -

full design 3 8 10 21 33 -

construction 2 30 32 25 -

transfer 10 10 0 -

punch list 15 5 20 0 -

= 118

Monthly plan 8 7 6 17 10 55 15

Cumulative - - - - - - -

Monthly actual 8 11 8 11 10 30 0

Cumulative Actual - - - - - - -

scheduleVariances

Planned value ( PV) -----------------------------

Earned Value (EV ) -------------------------------

Schedule Performance Index ---------------------------------

Estimated Time to completion --------------------------------

Cost Variances

Actual Cost of work performed (AC) ------------------------

Earned Value (EV) ------------------------------------------------

Cost Performance index -----------------------------------------

Estimated Cost to completion-----------------------------------

1) Calcualate the cumulative planned value

2) Calculatethe cumulative actual value

3) Calculate the earned value ( multiply the plan by the % complete)

4 ) Calculate SPI = EV / PV

5) Calculate ETC = 1/ (SPI) x time

6) Calculate CPI = EV /AC

7) Calculate ECC = 1/ ( CPI) x budget

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management The Managerial Process

Authors: Eric W Larson, Clifford F. Gray

8th Edition

1260570436, 978-1260570434

More Books

Students also viewed these General Management questions