Question
EVM Question January feb mar april may june july plan %comp value Activity staffing 8 7 15 100 - blueprinting 4 6 10 80 -
EVM Question January feb mar april may june july plan %comp value
Activity
staffing 8 7 15 100 -
blueprinting 4 6 10 80 -
Prototype development 2 8 10 60 -
full design 3 8 10 21 33 -
construction 2 30 32 25 -
transfer 10 10 0 -
punch list 15 5 20 0 -
= 118
Monthly plan 8 7 6 17 10 55 15
Cumulative - - - - - - -
Monthly actual 8 11 8 11 10 30 0
Cumulative Actual - - - - - - -
scheduleVariances
Planned value ( PV) -----------------------------
Earned Value (EV ) -------------------------------
Schedule Performance Index ---------------------------------
Estimated Time to completion --------------------------------
Cost Variances
Actual Cost of work performed (AC) ------------------------
Earned Value (EV) ------------------------------------------------
Cost Performance index -----------------------------------------
Estimated Cost to completion-----------------------------------
1) Calcualate the cumulative planned value
2) Calculatethe cumulative actual value
3) Calculate the earned value ( multiply the plan by the % complete)
4 ) Calculate SPI = EV / PV
5) Calculate ETC = 1/ (SPI) x time
6) Calculate CPI = EV /AC
7) Calculate ECC = 1/ ( CPI) x budget
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started