EX 1 3 - 3 ( Algo ) Given the following project network... Given the following project network and baseline information below, complete the form

EX13-3(Algo) Given the following project network...
Given the following project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8.
Time Period
Task DUR ES LF SL Budget (PV)123456789101112131415
A 2020420200220
B 62802300200500200600200600
C 52921500200400500100300
D 481201630430400400400
E 371221000400400200
F 312150610200110300
Period PV total 2002204009007007005001,000830600400400200110300
Cumulative PV total 2004208201,7202,4203,1203,6204,6205,4506,0506,4506,8507,0507,1607,460
(Do not round intermediate calculations. Round your table answer entries to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Human Resource Management Employees And Employers In Action

Authors: Cynthia Fontelle, Louis Bevoc

1st Edition

1688510249, 978-1688510241

More Books

Students also viewed these General Management questions

Question

Are the hours flexible or set?

Answered: 1 week ago

Question

Has each action got a clear and measurable outcome?

Answered: 1 week ago

Question

Have you eliminated jargon and unexplained acronyms?

Answered: 1 week ago