EX 6 - 2 1 ( Algo ) Given the following information, compute... Given the following information, compute the early, late, and slack times for
EXAlgo Given the following information, compute...
Given the following information, compute the early, late, and slack times for the project network.
ID Task Duration Predecessor Additional Lag Relationships Lag
A Interview users
B Define new features A Startstart A to B
Finishfinish A to B
C Order components B
D Build prototype C Finishstart C to D
E Test C Finishstart C to E
Finishfinish D to E
F Field test E