Exam # 2 Redo Problems On February 1 , 2 0 1 8 , Arrow Construction Company entered into a three - year construction contract

Exam #2 Redo Problems
On February 1,2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,360,000. During 2018, costs of $2,120,000 were incurred with estimated costs of $4,120,000 yet to be incurred. Billings of $2,620,000 were sent, and cash collected was $2,370,000.
In 2019, costs incurred were $2,620,000 with remaining costs estimated to be $3,780,000.2019 billings were $2,870,000 and $2,595,000 cash was collected. The project was completed in 2020 after additional costs of $3,920,000 were incurred. The company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Required:
Prepare journal entries to recognize revenue for 2018,2019 and 2020.|
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting And Causal Effects Econometric Challenges

Authors: Douglas A Schroeder

1st Edition

1441972242, 9781441972248

More Books

Students also viewed these Accounting questions

Question

4.6 Summarize job design concepts.

Answered: 1 week ago

Question

4.5 Explain what competencies and competency modeling are.

Answered: 1 week ago