Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Example 2 . 2 9 A project has the following activities as given in Table 2 . 1 0 7 and other activity - related

Example 2.29
A project has the following activities as given in Table 2.107 and other activity-related characteristics.
Table 2.107 Project activity details
Activity Predecessor(s) To
(Weeks) Tm (Weeks) Tp
(Weeks)
A 4716
B 1515
C A 61230
D A 258
E C 51117
F D 3615
G B 3927
H E, F 147
I G 41928
(a) Draw the PERT network.
(b) Identify the critical path.
(c) Determine the mean project completion times.
(d) Find the probability that the project is completed in 36 weeks.
(e) If the project manager wishes to be 99% sure that the project is completed, how many days
should be provided for the project work?
Solution:
(b) A C E H (c)37 weeks (d)42.07%(e)48.63 ~ 49 weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management

Authors: Harvey maylor

4th Edition

027370432X, 978-0273704324

More Books

Students also viewed these General Management questions

Question

Determine miller indices of plane X z 2/3 90% a/3

Answered: 1 week ago

Question

Describe the three types of data flows.

Answered: 1 week ago