Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Example (EAC) Case-III: You have a fixed deadline project with a budgeted cost of 600,000 USD. So far you have spent 300,000 USD and the
Example (EAC) Case-III: You have a fixed deadline project with a budgeted cost of 600,000 USD. So far you have spent 300,000 USD and the value of the completed work is 275,000 USD. However, as per the schedule you should have earned 325,000 USD to date. Calculate the Estimate at Completion (EAC). Solution: Given in the question: Budget at Completion (BAC) = 600,000 USD Actual Cost (AC) = 300,000 USD Earned Value (EV) = 275,000 USD Planned Value (PV) = 325,000 USD To calculate the EAC, first you have to calculate the CPI and SPI. SPI = EV/PV = 275,000/325,000 = 0.85 CPI = EV/AC = 275,000/300,000 = 0.92 Now, you can use the formula EAC = AC + (BAC - EV)/(CPI*SPI) = 300,000 + (600,000 - 275,000)/(0.85*0.92)= 300,000 + 325,000/0.78 = 300,000 + 416,000 = 716,000 Hence, the Estimate at Completion is 716,000 USD. an\": Pra ti ti 11' You have a project with a budgeted cost of 300,000 USD. So far you have spent 100,000 USD and the value of the completed work is 80,000 USD. However, as per the schedule you should have earned 90,000 USD to date. Client is insisting to complete the project on time. Calculate the Estimate at Completion (EAC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started