Examples of organizational process assets updates resulting from the Control Schedule process include: Select one: a. Lessons learned, causes of variance and the reasoning behind
Examples of organizational process assets updates resulting from the Control Schedule process include: Select one: a. Lessons learned, causes of variance and the reasoning behind the corrective actions chosen. b. Revenue achieved from the sale of the project's product. c. Proposals for follow-up projects. d. New organization charts illustrating the available resources for the project