Excel Solutions needed: A company has two plants producing windmills with the following capacities: Vietnam: 27 per week New Mexico: 35 per week The company
Excel Solutions needed:
A company has two plants producing windmills with the following capacities:
- Vietnam: 27 per week
- New Mexico: 35 per week
The company has three customers with the following demands per week.
- Iowa Wind Mills: 15 per week
- Madrid Equipments: 18 per week
- Kiev Alternative Energy: 12 per week
Following are the transportation costs between each production plant and each customer.
Distribution centers
Plants Iowa Madrid Kiev
Vietnam 650 700 600
New Mexico 450 560 700
a) Build a transportation network.
b) Write down a linear program that optimizes transportation cost.
c) Solve the LP using excel solver and interpret the solution.
(Make sure to upload the Excel worksheet)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started