Question
Executive Shirt Company, Inc. The Executive Shirt Company (ESC) had built a solid reputation in the apparel industry by supplying several well-known labels with high-quality,
Executive Shirt Company, Inc.
The Executive Shirt Company (ESC) had built a solid reputation in the apparel industry by
supplying several well-known labels with high-quality, competitively-priced men's dress shirts.
Prompted by a recent dip in ESC's sales, general manager Dwight Collier had decided to expand the
company's product line to take advantage of what he thought was a tremendous opportunity in the
custom-sized dress shirt market. Custom-sized shirts currently commanded a substantial price
premium: customers paid at least 75% more for a custom-made shirt than for an off-the-shelf shirt of
the same quality and construction. In addition, customers often waited 6 weeks or longer for delivery
of their custom-sized shirts. Collier thought that many men who currently bought off-the-shelf shirts
would prefer custom-made shirts, but were deterred by high prices and long delivery times. After
several retailers ESC currently supplied expressed enthusiasm for ESC's expansion into custom shirts,
Collier decided to begin production of a line of moderately-priced custom-made dress shirts that
would be delivered within 10 working days after the customer placed the order. Collier expected
ESC's custom shirts to command a $10 wholesale and $20 retail price premium over ESC's standardsized shirts. This plan was not too far-fetched: Levi-Strauss's popular custom-fit women's jeans were
delivered in 2 weeks and were priced at retail only $10 more than regular jeans.
The ESC Production Facility
ESC's current production process was designed to make large volumes of shirts with limited
product variety and relatively constant demand. Shirts were offered in a few basic styles and colors;
for example, white and blue shirts constituted over 80% of the company's total sales volume. All
production took place using a traditional batch process in ESC's Pauquet, Mississippi factory.
The Pauquet shop floor was divided into work areas where the different operations required
to cut and assemble a shirt were performed (Exhibit 1). Shirt patterns1 were cut on a computercontrolled cutting machine that could cut as many as 60 layers of cloth (of the same or multiple
colors) at the same time. The factory's current policy was to layout and cut 60 layers of cloth at a
time. Setting up the machine was a laborious process?it took about 1.5 minutes to carefully roll out
each layer of fabric on the cutting table (a total of 90 minutes for 60 layers). Patterns for up to 8 shirts
could be laid out at the same time (Exhibit 2). Thus, for each shirt pattern laid out, pieces for 60 shirts
1 A shirt pattern was a template which included all of the components of a shirt (sleeves, back, cuffs, etc.).
of the same style and size would be cut simultaneously. Once the fabric was laid out, it took on
average 30 minutes to cut all pieces for the 8 patterns from the cloth and remove them from the
cutting table. Cutting took the same amount of time regardless of the number of layers of cloth being
cut. The four cutting machine operators were fully utilized while the cloth was being laid out and
cut.
After cutting, the shirts were batched into batches of parts to make 60 shirts. The batches
were then sent to sewing, where 12 operations were performed before the finished shirts were
inspected, ironed, and packed (Exhibit 3). The sewing operations all used similar sewing machines.
Bins, each containing one batch of 60 shirts (or pieces for 60 shirts), were wheeled from one operation
to another by 4 material handlers. On average there were 3 batches of shirts for each worker (postcutting), including the batch that was currently being worked on at that station. A total of 64 direct
workers (performing all the operations from cutting to packaging) worked a single 8-hour shift,2 5
days a week, 20 days per month. The 4 material handlers and 64 direct workers were each paid $6.00
per hour (excluding benefits) on the regular shift, and $9.00 per hour on overtime, although overtime
was seldom used (see Exhibit 4 for the cost structure for a standard-sized shirt).
Planning the Custom Shirt Line
Collier knew that the introduction of a custom-sized shirt line would require some changes to
the manufacturing process. As a first step, Collier ordered a new "low-ply" laser cutting machine.
The new cutting machine was small: it could cut only one shirt pattern at a time out of up to 5 layers
of cloth. However, this new machine was extremely fast: the entire process of laying out a pattern
and cutting the shirts took only 2.5 minutes. Cutting only one pattern at a time rather than 8 would
result in a higher scrap rate?Collier estimated that material costs for custom-sized shirts would be
about 10% higher than for standard-sized shirts. Collier expected that any plan for manufacturing
custom-sized shirts would require hiring a new worker to operate the new machine; the existing
cutting machine would continue to be operated by a dedicated team of 4 workers.
Collier wanted to study several options for designing the manufacturing process for the
custom shirt line. He asked two of his managers, Mike and Ike, to come up with plans for
incorporating production of custom shirts into the existing manufacturing process. He specified only
that the manufacturing lead time for the custom shirts had to be less than 5 working days, and the
plans should initially allow for production of 2,000 custom shirts per month. The factory was
currently producing standard-sized shirts at a volume of 16,000 per month. The production volume
of the standard-sized shirts was expected to remain the same. He also cautioned Mike and Ike
against making large capital expenditures before this foray into the custom-shirt market had proven
to be successful.
Mike's Plan (Exhibit 5)
Mike thought that ESC should require a minimum order quantity of 5 custom shirts of a
given size, and devised his plan accordingly. He believed that the current production facilities could
easily accommodate the increased volume represented by the custom shirt line. The new cutting
machine could be set up next to the existing cutting machine, and would be run by the one new
worker dedicated to that machine. Regular shirts would be cut on the old machine, while custom
shirts would be cut on the new machine. Batches of custom shirts would be sewn with batches of
regular shirts. In order to shorten the lead time and to accommodate batches of 5 custom-sized shirts
2 Workers worked from 8:00 AM to 5:00 PM with one hour of unpaid lunch and no formal breaks. Workers
took informal breaks as desired and as allowed by their workload.
coming through the factory, Mike proposed reducing the batch size for all shirts from 60 to 5 shirts.
He also thought that it would be prudent to add extra batches of buffer inventory at each station after
cutting, for a total of 6 batches per worker.
Ike's Plan (Exhibit 6)
Ike, on the other hand, thought that custom-shirt production should be kept separate from
the production of standard-sized shirts. He proposed that all of the custom shirt operations, from
cutting to packaging, be done on a separate assembly line. Because there was excess capacity in the
factory, he proposed moving 1 worker from each sewing operation, 1 worker from inspection, 1
worker from ironing, and 1 worker from packaging to the new line. In addition, 12 sewing machines
and one ironing machine could be moved from the regular shirt production to the custom shirt line.
On the new line, each operator would perform the same operation he or she had been assigned in the
current factory, in the same sequence. Each operator would work on one shirt at a time, with an
average of 3 shirts for each of the 15 workers on the line (post-cutting). As in Mike's plan, one new
worker would be hired to operate the new cutting machine. Ike planned to leave the regular shirt
production process unchanged, except that each operation would be performed by one less worker
(except cutting). He thought that the reduction of people and equipment in the regular shirt
production area could easily be made up by asking the shift to work a small amount of overtime if
necessary.
Questions:
A)Compute the following quantities for the current production process as well as for Mike's and Ike's plans, assuming the plans are implemented as described in the case. All calculations MUST be carried out in Excel Spreadsheet.
Current Process
Regular
Shirts
Mike's Plan
Regular & Custom Shirts
Ike's Plan
Regular Shirts
Custom Shirts
Manufacturing Lead Time (days)
Work In Process Inventory (shirts)
Production Capacity (shirts/day)
Capacity Utilization
Direct Labor Content (min/shirt)
Direct Labor Cost ($/shirt)
*Assume 8-hours work day
B)Compare the two plans (IN DETAIL), in terms of both regular shirt production and custom shirt production. Based on your analysis, what is your recommendation for Dwight Collier?
Deliverables:
1.A report and your Excel Spreadsheet model. The Excel Spreadsheet model should clearly show all calculations. The report should explain the calculations carried out in the Excel model.
2.Oral Presentation in the last week of classes.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started