Question

1 Approved Answer

Exercise 1 ( Try it yourself ) During one 8 - hour shift, 7 5 0 nondefective parts are desired from an operation. The standard

Exercise 1(Try it yourself)
During one 8-hour shift, 750 nondefective parts are desired from an operation. The standard time for the operation is 15min. Because the machine operators are unskilled, the actual time it takes to perform the operation is 20min and, on the average, one-fifth of the parts that begin fabrication are scrapped. Assuming that each of the machines used for this operation will not be available for 1hr each shift, determine the number of machines required.
41
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions