Exercise 15-5 Manufacturing cost flows LO P1, P2, P3 Custom Cabinetry has one job in process (Job 120) as of June 30, at that time, its job cost sheet reports direct materials of $8.000 direct labor of $3,400, and applied overhead of $2.720. Custom Cabinetry applies overhead at the rate of 80% of direct labor cost During July, Job 120 is sold on account) for $31.500. Job 121 is started and completed, and Job 122 is started and still in process at the end of the month Custom Cabinetry incurs the following costs during July July Product Costs Direct materials Direct labor Overhead applied Job 120 $1,900 3,600 Job 121 $6,500 4,800 Job 122 $3,800 2,400 Total $12,200 10.800 1. Prepare journal entries for the following in July a. Direct materials used in production b. Direct labor used in production c. Overhead applied. d. The sale of Job 120. e. Cost of goods sold for Job 120 2. Compute the July 31 balances of the Work in Process Inventory and the Finished Goods Inventory accounts. (Assume there are no jobs in Finished Goods Inventory as of June 30 ) Complete this question by entering vuran Required 1 Required 2 Prepare journal entries for the above transactions in July, View transaction list View journal entry worksheet Credit Debit 12,200 Record the entry to assign direct materials to job. 12,200 2 Record the entry to assign direct labor to job. 10.800 3 Record the application of overhead to work in process. 10,800 4 Record the sale of Job 120 on account. Required 2 > 5 Record cost of goods sold for Job 120. Note : = journal entry has been entered Required 1 Required 2 Compute the July 31 balances of the Work in Process Inventory and the Finished Goods Inventory general ledger accounts. (Assume there are no jobs in Finished Goods Inventory as of June 30.) Job Direct materials Direct labor Work in Process Finished Goods Job 1217 Job 122 6,500 $ 3,800 4,800 2.400 2,720 2.720 14,020 8.920 Overhead Total cost