CheyenneConstruction Company uses the percentage-of-completion method of accounting. In 2017, Cheyenne began work under contract #E2-D2, which provided for a contract price of $2,176,000. Other details follow:
2017 2018
Costs incurred during the year $698,750 $1,448,000
Estimated costs to complete, as of December 31 926,250 -0-
Billings to date 425,000 2,176,000
Collections during the year 355,000 1,508,000
What portion of the total contract price would be recognized as revenue in 2017? In 2018?
Revenue recognized in 2017 $___________
Revenue recognized in 2018 $___________
Provide a complete set of journal entries for 2017 (using the percentage-of-completion method)
-(To record cost of of construction.)
-(To record progress billings.)
-(To record collections.)
-(To recognize revenue.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started