Exercise 2 [ 5 0 pts ] The following vacuum cleaner company is performing the feasibility study of launching a new product. The following information
Exercise pts
The following vacuum cleaner company is performing the feasibility study of launching a new
product. The following information is gathered. This includes the product testing, manufacturing.
cost estimation, marketing research,... The activities that make up the project are identified with
their duration, their immediate predecessor, as well as the optimistic, most probable and
pessimistic duration for each activity are summarised in the following Table
Table : Information about the activities
Part : Here consider firat deterministic durations
i Construct the corresponding network
ii Using CPM determine the critical path and the total duration of the project.
iii Show the corresponding Gantt Chart and discuss bow long some of the activitiea could be
delayed without affecting your decision es; completing the project on time, consider
activity G say
Part : Now consider the uncertain duration:
Given the uncertain duration of the activities and the estimates given in Table use DERT to
a find the expected time and the variance for each activity.
b determine the corresponding critical path, the expected total duration of the project
and its corresponding variance.
c calculate the probability of completing the project within weeks.
please solve part and
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started