Exercise 2 A project consisting of 8 activities are described in the following table. The cost for completion of these 8 activities is 5 8

Exercise 2
A project consisting of 8 activities are described in the following table. The cost for completion of these 8 activities is 5800 excluding the site overhead. The overhead cost of general site activities is 160/day.
We are asked to:
(1) calculate and state the time for completion on a normal basis;
(2) calculate and state the critical path on this basis, and the cost;
(3) calculate and state the cost of completion in the shortest possible time.
\table[[Activity,\table[[Normal completion],[time (days)]],\table[[Shortest completion],[time (days)]],\table[[Cost of reduction per],[day (f)]]],[A (1-2),6,4,80],[B (1-3),8,4,90],[C (1-4),5,3,30],[D (2-4),3,3,-],[E (2-5),5,3,40],[F (3-6),12,8,200],[G (4-6),8,6,50],[H (5-6),6,6,-]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

What Is A Database And How Do I Use It

Authors: Matt Anniss

1st Edition

1622750799, 978-1622750795

More Books

Students also viewed these Databases questions

Question

Define language, and recognize its properties.

Answered: 1 week ago

Question

6. Explain the strengths of a dialectical approach.

Answered: 1 week ago