Exercise 2 A project consisting of 8 activities are described in the following table. The cost for completion of these 8 activities is 5 8
Exercise
A project consisting of activities are described in the following table. The cost for completion of these activities is excluding the site overhead. The overhead cost of general site activities is day
We are asked to:
calculate and state the time for completion on a normal basis;
calculate and state the critical path on this basis, and the cost;
calculate and state the cost of completion in the shortest possible time.
tableActivitytableNormal completiontime daystableShortest completiontime daystableCost of reduction perday fA B C D E F G H
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started