Exercise 24-12 Byrd Company produces one product, a putter called GO-Putter. Byrd uses a standard cost system and determines that it should take one hour
Exercise 24-12
Byrd Company produces one product, a putter called GO-Putter. Byrd uses a standard cost system and determines that it should take one hour of direct labor to produce one GO-Putter. The normal production capacity for this putter is 100,000 units per year. The total budgeted overhead at normal capacity is $900,000 comprised of $300,000 of variable costs and $600,000 of fixed costs. Byrd applies overhead on the basis of direct labor hours.
During the current year, Byrd produced 72,700 putters, worked 82,300 direct labor hours, and incurred variable overhead costs of $130,860 and fixed overhead costs of $600,300.
Compute the predetermined variable overhead rate and the predetermined fixed overhead rate. (Round answers to 2 decimal places, e.g. 2.75.) Variable Fixed Predetermined Overhead Rate LINK TO TEXT LINK TO VIDEO Compute the applied overhead for Byrd for the year. Overhead Applied LINK TO TEXT LINK TO VIDEO Compute the total overhead variance. Total Overhead Variance $ Click if you would like to Show Work for this question: Open Show WorkStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started