Exercise 3-17 (Algo) Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO3-1, LO3-2, LO3-3, LO3-4] Skip to question [The following information applies to the questions

Exercise 3-17 (Algo) Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO3-1, LO3-2, LO3-3, LO3-4]

Skip to question

[The following information applies to the questions displayed below.]

Delph Company uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company estimated that 53,000 machine-hours would be required for the periods estimated level of production. It also estimated $980,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $5.00 per machine-hour.

Because Delph has two manufacturing departmentsMolding and Fabricationit is considering replacing its plantwide overhead rate with departmental rates that would also be based on machine-hours. The company gathered the following information to enable calculating departmental overhead rates:

Molding Fabrication Total
Machine-hours 22,000 31,000 53,000
Fixed manufacturing overhead cost $ 760,000 $ 220,000 $ 980,000
Variable manufacturing overhead cost per machine-hour $ 5.00 $ 1.00

During the year, the company had no beginning or ending inventories and it started, completed, and sold only two jobsJob D-70 and Job C-200. It provided the following information related to those two jobs:

Job D-70 Molding Fabrication Total
Direct materials cost $ 370,000 $ 320,000 $ 690,000
Direct labor cost $ 240,000 $ 160,000 $ 400,000
Machine-hours 14,000 8,000 22,000
Job C-200 Molding Fabrication Total
Direct materials cost $ 260,000 $ 260,000 $ 520,000
Direct labor cost $ 120,000 $ 260,000 $ 380,000
Machine-hours 8,000 23,000 31,000

Delph had no underapplied or overapplied manufacturing overhead during the year.

Exercise 3-17 (Algo) Part 1

Required:

  1. Assume Delph uses plantwide predetermined overhead rates based on machine-hours.
    1. Compute the plantwide predetermined overhead rate.
    2. Compute the total manufacturing cost assigned to Job D-70 and Job C-200.
    3. If Delph establishes bid prices that are 150% of total manufacturing costs, what bid prices would it have established for Job D-70 and Job C-200?
    4. What is Delphs cost of goods sold for the year?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions