Exercise 4-10 Contrasting ABC and Conventional Product Costs [LO4-2, LO4-3, LO4-4) Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 65.20 $ 18.60 1.4 DLHS 29,000 units Pathbreaker $ 51.40 $ 13.40 1 DLHS 79,000 units The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours for the upcoming year appear below: Estimated total manufacturing overhead Estimated total direct labor-hours $2,439,840 119,600 DLHS Required: 1-a. Compute the predetermined overhead rate based on direct labor-hours. 1-b. Using the predetermined overhead rate and other data from the problem, determine the unit product cost of each product 2. The company is considering replacing its conventional costing system with an activity-based costing system that would assign its manufacturing overhead to the following four activity cost pools: Activity Cost Pools and Activity Measures Supporting direct labor (direct labor-hours) Batch setups (setups) Product sustaining (number of products) General factory (machine-hours) Total manufacturing overhead cost Estimated Overhead Cost $ 891,020 836,000 632,360 80,460 $2,439,840 Expected Activity Xactive Pathbreaker Total 40,600 79,000 119,600 270 170 440 1 1 2 2,900 7,900 10,800 Determine the activity rate for each of the four activity cost pools. 3. Using the activity rates and other data from the problem, determine the unit product cost of each product. ces Complete this question by entering your answers in the tabs below. Reg 1A Reg 1B Reg 2 Reg 3 Compute the predetermined overhead rate based on direct labor-hours. (Round your answer to 2 decimal places.) Predetermined overhead rate per DLH Determine the activity rate for each of the four activity cost pools. 3. Using the activity rates and other data from the problem, determine the unit product cost of each product. Complete this question by entering your answers in the tabs below. Req 1A Rea Reg 2 Reg 3 Using the predetermined overhead rate and other data from the problem, determine the unit product cost of each product. (Round your intermediate calculations and final answers to 2 decimal places.) Xactive Pathbreaker Unit product cost Determine the activity rate for each of the four activity cost pools. 3. Using the activity rates and other data from the problem, determine the unit product cost of each product. s Complete this question by entering your answers in the tabs below. Req 1A Reg 1B Req I Req3 Determine the activity rate for each of the four activity cost pools. (Round your "per DLH" and "per MHR" answers to 2 decimal places.) Activity Cost Pools Activity Rato Supporting direct labor Batch setups per setup Product sustaining por product General factory per MHR per DLH Reg 1B Rua 3 Determine the activity rate for each of the four activity cost pools. 3. Using the activity rates and other data from the problem, determine the unit product cost of each product. Complete this question by entering your answers in the tabs below. Reg 1A Reg 1B Reg 2 Req Using the activity rates and other data from the problem, determine the unit product cost of each product. (Round your intermediate calculations and final answers to 2 decimal places.) Xactive Pathbreaker Unit product cost