Question
Exercise 7-16 (Algorithmic) Cost control evaluation HardHead makes precast concrete steps for use with manufactured housing. The company had the following 2013 budget based on
Exercise 7-16 (Algorithmic)
Cost control evaluation
HardHead makes precast concrete steps for use with manufactured housing. The company had the following 2013 budget based on expected production of 6,800 units:
Standard Cost | Amount Budgeted | |
Direct material | $21.15 | $143,820 |
Direct labor | 11.60 | 78,880 |
Variable overhead | ||
Indirect material | 4.35 | 29,580 |
Indirect labor | 1.90 | 12,920 |
Utilities | 1.20 | 8,160 |
Fixed overhead | ||
Supervisory salaries | 85,340 | |
Depreciation | 30,940 | |
Insurance | 23,460 | |
Total | $413,100 |
Cost per unit = $413,100 6,800 = $60.75
Actual production for 2013 was 7,600 units, and actual costs for the year were as follows:
Direct material used | $168,340 |
Direct labor | 88,540 |
Variable overhead | |
Indirect material | 31,160 |
Indirect labor | 15,808 |
Utilities | 10,184 |
Fixed overhead | |
Supervisory salaries | 87,392 |
Depreciation | 30,940 |
Insurance | 21,560 |
Total | $453,924 |
Cost per unit = $453,924 7,600 = $59.73
The plant manager, Tanzi Palate, whose annual bonus includes (among other factors) 20 percent of the net favorable cost variances, states that he saved the company $7,752 [($60.75 - $59.73) X 7,600]. He has instructed the plant cost accountant to prepare a detailed report to be sent to corporate headquarters comparing each component's actual per-unit cost with the per-unit amounts in the preceding annual budget to prove the $7,752 cost savings.
a. Is the actual-to-budget comparison proposed by Palate appropriate? --Inappropriate Correct
If his comparison is not appropriate, prepare a more appropriate comparison. In the Variance column, enter a "U" for an unfavorable variance or an "F" for a favorable variance and if no variance use "NA". If an amount is zero, enter "0".
b. How would you, as the plant cost accountant, react if Palate insisted on his comparison? Suggest what alternatives are available to you.
--
I need help with the second part of part A and with Part B. The number I have in the Blue column under Actual is WRONG, but all the labels to the left of it are CORRECT.
Thanks in Advance
his comparison is not appropriate, prepare a more appropriate comparison. In the variance column, enter a 'U' tor an unfavorable variance or an tor a tavorable vanance and IT variance use "NA". If an amount is zero, enter " HardHead Concrete Actual Busdgi Variance Direct Material 143820$ Direct Labor Variable OH Indirect Material Indirect Labor Utilities Fixed OH Supervisory Salaries Depreciation Insurance TotalsStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started