Exercise 7-29 (Algo) Predetermined Overhead Rates (LO 7-3) Southern Rim Parts estimates its manufacturing overhead to be $306,000 and its direct labor costs to be $1,020,000 for year 1. The first three jobs that Southern Rim worked on had actual direct labor costs of $61,000 for Job 301, $86,000 for Job 302, and $155,000 for Job 303. For the year, actual manufacturing overhead was $419,000 and total direct labor cost was $838,000. Manufacturing overhead is applied to jobs on the basis of direct labor costs using predetermined rates, Required: a. How much overhead was assigned to each of the three jobs, 301, 302, and 303? b. What was the over- or underapplied manufacturing overhead for year 1? Complete this question by entering your answers in the tabs below. Required A Required B How much overhead was assigned to each of the three jobs, 301, 302, and 303? Job 301 Job 302 Job 303 Red Required B Exercise 7-29 (Algo) Predetermined Overhead Rates (LO 7-3) Southern Rim Parts estimates its manufacturing overhead to be $306,000 and its direct labor costs to be $1,020,000 for year 1. The first three jobs that Southern Rim worked on had actual direct labor costs of $61,000 for Job 301, $86,000 for Job 302, and $155.000 for Job 303. For the year, actual manufacturing overhead was $419,000 and total direct labor cost was $838,000. Manufacturing overhead is applied to jobs on the basis of direct labor costs using predetermined rates. Required: a. How much overhead was assigned to each of the three jobs, 301, 302, and 303? b. What was the over- or underapplied manufacturing overhead for year 17 Complete this question by entering your answers in the tabs below. Required A Required B what was the over- or underapplied manufacturing overhead for year 1? manufacturing overhead