Exercise: Bake a CakeMake a Network DiagramDetermine the Critical Path using the Forward and Backward Pass. What is the duration of the project?ID Activity Duration

Exercise: Bake a CakeMake a Network DiagramDetermine the Critical Path using the Forward and Backward Pass. What is the duration of the project?ID Activity Duration Pred. A Find recipe 10B Preheat oven 10 AC Measuring 15 AD Frosting 15 CE Batter 20 CF Bake 30 B,EG Decorate 15 D,FBased on the table below, please make a network diagram using MS Visio or Word. Also please calculate and show the ES, EF, LS, and LF times along with the slack for each activity using the critical path methodology.Based on your completed network diagram please answer the following questions.1. What is the critical path for the project at the end of the planning process?2. At the end of the planning process, can the project meet its required completion date? What is its estimated completion

image text in transcribed
Required completion is 30 weeks. Estimated Actual Activity Time Finish Time (Weeks) (Weeks) Immediate Predecessor

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: John Pearce , Richard Robinson

13th Edition

0078029295, 978-0078029295

More Books

Students also viewed these General Management questions

Question

=+ a. What is the per-worker production function?

Answered: 1 week ago