Exercise C: Activity-Based Costing Erte, Inc. has the following predicted indirect costs and cost drivers for 2017 for the given activity cost pools: Manufacture Department

Exercise C: Activity-Based Costing

Erte, Inc. has the following predicted indirect costs and cost drivers for 2017 for the given activity cost pools:

Manufacture Department

Finishing Department

Cost Driver

Maintenance

$30,000

$15,000

Machine hours

Materials handling

$40,000

$25,000

Material moves

Machine setups

$80,000

$5,000

Machine setups

Inspections

$0

$20,000

Inspection hours

Total

150,000

$65,000

The following activity predictions were also made for the year:

Manufacture Department

Finishing Department

Machine hours

15,000

8,000

Materials moves

5,000

3,500

Machine setups

900

150

Inspection hours

0

3,000

It is assumed that the cost per unit of activity for a given activity does not vary between departments. The companys president is trying to evaluate the companys product mix strategy regarding two of its four product models, K200 and V400. The company has been using a company-wide overhead rate based on machine hours but is considering switching to either department rates or activity-based rates. The production manager has provided the following data for the production of a batch of 150 units for each of these models:

K200

V400

Direct materials cost

$15,000

$22,000

Direct labor cost

$7,000

$6,000

Machine hours (Manufacture)

700

900

Machine hours (Finishing)

400

300

Materials moves

60

80

Machine setups

9

12

Inspection hours

60

80

Required:

  1. Determine the cost of one unit each of K200 and V400, assuming a company-wide overhead rate is used based on total machine hours.
  2. Determine the cost of one unit each of K200 and V400, assuming department overhead rates are used. Overhead is assigned based on machine hours in both departments.
  3. Determine the cost of one unit each of K200 and V400, assuming activity-based overhead rates are used for maintenance handling, machine setup, and inspection activities.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions