Exercise Minimizing handling work in storage Weekly demand of one spare part from a big maintenance storage is 100 pieces, and in average the maintenance

Exercise Minimizing handling work in storage

Weekly demand of one spare part from a big maintenance storage is 100 pieces, and in average the maintenance spare part order size is 2 pieces per order.

The purchasing lot size is 1000 pieces and the deliveries arrive when needed.

The picking time for this type of items is 3 minutes per order row and handling time in incoming material 20 minutes per delivery.

a.Calculate the yearly picking time and handling time of incoming deliveries for this item.

b.If this fast mowing item is placed far from active picking area, the picking time is easily 20 % longer than if it is located in the actual picking area. Calculate the extra cost if these items are not located correctly, when you know that the salary for storage worker is 10 an hour + 65 % side cost.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Linda Smith Bamber, Karen Wilken Braun, Jr. Harrison, Walter T.

1st Edition

0138129711, 978-0138129712

More Books

Students also viewed these Accounting questions

Question

2. Do you agree that unions stifle creativity? Why or why not?

Answered: 1 week ago