Question
1 Approved Answer
Exhibit 11-2 Expected Cash Flows Year Project L Project S 0 ($100) ($100) 1 10 70 2 60 50 3 80 20 Both projects have
Exhibit 11-2
Expected Cash Flows Year Project L Project S
0 ($100) ($100)
1 10 70
2 60 50
3 80 20
Both projects have a cost of capital of 10%.
5. Refer to Exhibit 11-2. What is Project L's NPV?
6. Refer to Exhibit 11-2. What is Project L's IRR?
7. Refer to Exhibit 11-2. What is Project L's MIRR?