Exhibit 3. 3 Use a spreadsheet to schedule an operation with a base quantity of 100 units, and 2 splits. It has a setup time of 30 minutes, a machine time of 20 minutes, a labor time of 4 minutes, and a teardown time of 20 minutes. 6 Question 26 (1 point) Refer to Exhibit 3. Calculate time of each component and the total time in minutes allocated for the operation in order to produce 3,500 units. 9 1.960 12 980 56 15 470 725 Question 27 (1 point) kerer to Exhibit 3. Calculate time or each component ana the total time in minutes allocated for the operation in order to produce 3,500 units. 1,960 980 56 470 725 Question 27 (1 point) Refer to Exhibit 3. Calculate time of each component and the total time in minutes allocated for the operation in order to produce 7,000 units. 1,960 890 56 255 1,725 Question 28 (1 point) Refer to Exhibit 3. Calculate time of each component and the total time in minutes allocated for the operation in order to produce 7,000 units with 4 splits. 1,960 980 56 470 725 Exhibit 3. 3 Use a spreadsheet to schedule an operation with a base quantity of 100 units, and 2 splits. It has a setup time of 30 minutes, a machine time of 20 minutes, a labor time of 4 minutes, and a teardown time of 20 minutes. 6 Question 26 (1 point) Refer to Exhibit 3. Calculate time of each component and the total time in minutes allocated for the operation in order to produce 3,500 units. 9 1.960 12 980 56 15 470 725 Question 27 (1 point) kerer to Exhibit 3. Calculate time or each component ana the total time in minutes allocated for the operation in order to produce 3,500 units. 1,960 980 56 470 725 Question 27 (1 point) Refer to Exhibit 3. Calculate time of each component and the total time in minutes allocated for the operation in order to produce 7,000 units. 1,960 890 56 255 1,725 Question 28 (1 point) Refer to Exhibit 3. Calculate time of each component and the total time in minutes allocated for the operation in order to produce 7,000 units with 4 splits. 1,960 980 56 470 725