Answered step by step
Verified Expert Solution
Question
1 Approved Answer
EZ. You are the manager of a new clothing store scheduled to open next week. Before you can open the store, there are seven
EZ. You are the manager of a new clothing store scheduled to open next week. Before you can open the store, there are seven major tasks that need to be completed. You have two employees that are responsible for getting the tasks done. Some tasks can't be completed until other tasks are finished (the order of which is given by the following table). The processing times for each task are also given. a. Draw a precedence digraph to represent the tasks. Task A B C D E F G Processing Prerequisite Time Tasks? 4 hours None 5 hours None 3 hours A, B 6 hours 5 hours 8 hours 2 hours b. Find the critical path and critical time for the project by using the Backflow Algorithm. None A D C, E, F c. Use the following priority list to schedule the tasks for your employees. What is the finishing time? (B,A,E,C,D,F,G) d. Do you think the finishing time in part (c) is the fastest way to get the job done? Why? If yes, explain why. If no, explain why the priority list was inefficient and how it could be improved.
Step by Step Solution
★★★★★
3.37 Rating (141 Votes )
There are 3 Steps involved in it
Step: 1
a Draw a precedence diagram This diagram will show the tasks and their prerequisites b Find the crit...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started