f the net present value of a project is zero based on a discount rate of 16%, then the internal rate of return is: Multiple

f the net present value of a project is zero based on a discount rate of 16%, then the internal rate of return is:

Multiple Choice

greater than 16%.

equal to 16%.

cannot be determined from this data.

less than 16%.