Question

1 Approved Answer

Fabric Plant: Budgeted overhead: $ 1 , 2 0 0 , 0 0 0 ( 5 0 % fixed ) Practical volume ( direct labor

Fabric Plant:
Budgeted overhead: $1,200,000(50% fixed)
Practical volume (direct labor hours): 120,000 hours
Actual overhead: $1,150,000(50% fixed)
Actual hours worked (for each fabric type, department, and in total):
Grade
Weaving and
Pattern
Coloring and
Bolting Total
Fabric FB6020,00012,00032,000
Fabric FB7028,00014,00042,000
Fabric FB8026,00018,00044,000
Total 74,00044,000118,000
Departmental data on Fabric FB70(actual costs and actual outcomes):
Weaving and
Pattern
Coloring and
Bolting
Beginning inventories
Units*20,000400
Costs:
Transferred in $0 $100,000
Materials $80,000 $8,000
Labor $18,000 $6,600
Overhead $22,000 $9,000
Current production:
Units started 80,000?
Units transferred out 80,0003,200
Costs:
Transferred in $0?
Materials $320,000 $82,000
Labor $208,000 $99,400
Overhead ??
Percentage completion:
Beginning inventory 30%40%
Ending inventory 40%50%
*Units are measured in yards for the Weaving and Pattern Department and in bolts for the
Coloring and Bolting Department. Note: With the exception of the cardboard bolt rods, materials
5
2024, Jennifer K Howard. All rights reserved.
are added at the beginning of each process. The cost of the rods is relatively insignificant and is
included in overhead.
Proposed standard cost sheet for Fabric FB70(for the Coloring and Bolting Department only):
Transferred-in materials (25 yards @ $10) $250.00
Other materials (100 ounces @ $0.20)20.00
Labor (3.1 hours @ $8)24.80
Fixed overhead (3.1 hours @ $5)15.50
Variable overhead (3.1 hours @ $5)15.50
Standard cost per unit $325.80
The Questions:
1. Calculate the plantwide overhead rate for the fabric plant.
2. Calculate the amount of under- or overapplied overhead for the fabric plant.
3. Using the weighted average method, calculate the cost per bolt for Fabric FB70.
3A. Weaving and Pattern Department
i. Physical flow schedule
ii. EU schedule (DM, CC)
iii. Cost per EU (DM, CC)
You will need to calculate applied OH
iv. Cost of goods transferred out
3B. Coloring and Bolting Department
i. Physical flow schedule
You will need to convert from yards to bolts
ii. EU schedule (Transferred-in, DM, CC)
iii. Cost per EU (Transferred-in, DM, CC)
You will need to calculate applied OH
3C. Unit cost of a bolt of Fabric FB70

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Susan S. Hamlen

4th Edition

1618532618, 9781618532619

More Books

Students also viewed these Accounting questions

Question

2. Visualize your staff as a whole and each person in it.

Answered: 1 week ago

Question

1. Arouse curiosity with questions such as What would happen if?

Answered: 1 week ago