FACT SCENARIO D (Questions 13-18): Geddy Construction (GC) has a written contract with Owner to renovate an existing meat processing plant in Lawton, Oklahoma. The

FACT SCENARIO D (Questions 13-18):

Geddy Construction (GC) has a written contract with Owner to renovate an existing meat processing plant in Lawton, Oklahoma. The contract is governed by the 2017 Edition of AIA Document A201. GC executes a written subcontract with Subterranean Construction (Sub) to perform a portion of the work. Because of delays, Owner withholds payment from GC who, in turn, withholds payment from Sub. Sub is contemplating filing a lien against Owner's property.

Question

In Oklahoma, the pre-lien notice requirement does not apply to:

Group of answer choices

  • Claims for less than $10,000
  • Suppliers
  • Second-tier subcontractors
  • General contractors
  • Retainage
  • Where work is performed under an oral contract

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Business Law And Its Environment

Authors: Richard Schaffer, Filiberto Agusti, Lucien J. Dhooge, Beverley Earle

8th Edition

0538473614, 978-0538473613

More Books

Students also viewed these Law questions

Question

Are the hours flexible or set?

Answered: 1 week ago