FACT SCENARIO D (Questions 13-18): Geddy Construction (GC) has a written contract with Owner to renovate an existing meat processing plant in Lawton, Oklahoma. The

FACT SCENARIO D (Questions 13-18):

Geddy Construction (GC) has a written contract with Owner to renovate an existing meat processing plant in Lawton, Oklahoma. The contract is governed by the 2017 Edition of AIA Document A201. GC executes a written subcontract with Subterranean Construction (Sub) to perform a portion of the work. Because of delays, Owner withholds payment from GC who, in turn, withholds payment from Sub. Sub is contemplating filing a lien against Owner's property.

Question

Under Oklahoma law, how long does Sub have to record a lien?

Group of answer choices

45 days from the date of last performance

75 days from the date of last performance

90 days from the date of last performance

120 days from the date of last performance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Family Law

Authors: Douglas Abrams, Naomi Cahn, Catherine Ross, Linda McClain

5th Edition

1640205918, 978-1640205918

More Books

Students also viewed these Law questions