FACT SCENARIO E (Questions 19-22): Geddy Construction (GC) has a written contract with Owner, an Oklahoma municipality, to build a sewer treatment plant with three
FACT SCENARIO E (Questions 19-22):
Geddy Construction (GC) has a written contract with Owner, an Oklahoma municipality, to build a sewer treatment plant with three lagoons. The prime contract is governed by the 2017 Edition of AIA Document A201. Owner hired YYZ Design (YYZ) to prepare the plans and specifications. YYZ, in turn, hired an independent lab to perform a comprehensive soils test. Based on the results of the soils test, the plans and specifications prepared by YYZ called for the installation of bentonite-treated clay liners in the three lagoons. The specified mix ratio was 3%. Significant leaks appeared shortly after the lagoons were constructed and filled with water. The project was shut down for 3 months while the source of the leaks and a possible solution were investigated. GC, Owner, and YYZ subsequently determine that the specified bentonite mix ratio of 3% was inadequate to properly seal the floor of the lagoons. At the Owner's request, GC prepares a cost estimate to rework the clay liners with additional bentonite. After receiving GC's cost estimate, the Owner and YYZ decide that GC should have recognized the error in the specifications and reported the problem before the clay liners were first installed. The Owner and YYZ issue a change directive requiring GC to proceed with the remedial work at GC's own expense. In total, the project takes 6 months longer than expected and GC spends $150,000 on the lagoon repairs. YYZ is also the designated Initial Decision Maker (IDM).
Assume that GC submits a claim to YYZ for an increase in the contract price and/or contract time. If GC is dissatisfied with YYZ's decision, what must it and how long does it have to do it?
Group of answer choices
Demand mediation within 30 days.
File a lien within 120 days from the date if its final invoice.
File suit within 5 years after sending a pre-lien notice.
Demand arbitration within 4 months of the date of last performance.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started