FACT SCENARIO F (Questions 23-27): With regard to the notice and suit filing requirements which must be satisfied by subcontractors and suppliers in order to

FACT SCENARIO F (Questions 23-27):

With regard to the notice and suit filing requirements which must be satisfied by subcontractors and suppliers in order to successfully assert a claim on a prime contractor's public works payment bond under Title 61 Oklahoma Statutes, answer the following:

How long do subcontractors and suppliers, regardless of tier, have to file a lawsuit against the bond in order to preserve their bond claim?

Group of answer choices

1 year

1 month

6 months

3 years

90 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Law

Authors: Joanne Hames, Yvonne Ekern

4th edition

013502434X, 978-0135024348

More Books

Students also viewed these Law questions

Question

5. It is the needs of the individual that are important.

Answered: 1 week ago

Question

3. It is the commitment you show that is the deciding factor.

Answered: 1 week ago