Question

1 Approved Answer

Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $258,000 Fixed factory

Factory Overhead Cost Variances

The following data relate to factory overhead cost for the production of 8,000 computers:

Actual: Variable factory overhead $258,000
Fixed factory overhead 61,750
Standard: 8,000 hrs. at $38 304,000

If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $327,750, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $4.75 per hour. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

image text in transcribed

Variance Amount Favorable/Unfavorable Variable factory overhead controllable variance $ Fixed factory overhead volume variance Total factory overhead cost variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Comprehensive Assurance & Systems Tool

Authors: Laura R. Ingraham, Greg Jenkins

4th Edition

0134790472, 9780134790473

More Books

Students also viewed these Accounting questions

Question

Are there any disadvantages to this tactic?

Answered: 1 week ago

Question

Who is the assigned manager for each tactic?

Answered: 1 week ago