Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $101,750 Fixed factory
Factory Overhead Cost Variances
The following data relate to factory overhead cost for the production of 8,000 computers:
Actual: | Variable factory overhead | $101,750 |
Fixed factory overhead | 180,000 | |
Standard: | 8,000 hrs. at $31 | 248,000 |
If productive capacity of 100% was 10,000 hours and the factory overhead cost budgeted at the level of 8,000 standard hours was $284,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $18 per hour.
Enter a favorable variance as a negative amount, and an unfavorable variance as a positive amount.
Variance | Amount | Favorable/Unfavorable | ||
Controllable | Favorable | |||
Volume | 36,000 | Unfavorable | ||
Total factory overhead cost variance | 33,750 | Unfavorable |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started