Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $98,500 Fixed factory
Factory Overhead Cost Variances
The following data relate to factory overhead cost for the production of 7,000 computers:
Actual: | Variable factory overhead | $98,500 |
Fixed factory overhead | 38,500 | |
Standard: | 7,000 hrs. at $18 | 126,000 |
If productive capacity of 100% was 11,000 hours and the factory overhead cost budgeted at the level of 7,000 standard hours was $140,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $3.5 per hour. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Variance | Amount | Favorable/Unfavorable |
Controllable variance | $ | Favorable |
Volume variance | $ | Unfavorable |
Total factory overhead cost variance: | $ | Unfavorable |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started