Factory Overhead Cost Variances Thomas Textiles Corporation began November with a budget for 38,000 hours of production in the Weaving Department. The department has a

Factory Overhead Cost Variances

Thomas Textiles Corporation began November with a budget for 38,000 hours of production in the Weaving Department. The department has a full capacity of 51,000 hours under normal business conditions. The budgeted overhead at the planned volumes at the beginning of November was as follows:

Variable overhead $117,800
Fixed overhead 81,600
Total $199,400

The actual factory overhead was $201,800 for November. The actual fixed factory overhead was as budgeted. During November, the Weaving Department had standard hours at actual production volume of 40,000 hours.

Determine the variable factory overhead controllable variance and the fixed factory overhead volume variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. Round your interim computations to the nearest cent, if required.

a. Variable factory overhead controllable variance: ? (Favorable)

b. Fixed factory overhead volume variance: ? (Favorable)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finance The Basics

Authors: Erik Banks

3rd Edition

1138919780, 9781138919785

More Books

Students also viewed these Accounting questions

Question

=+What is your personal mission statement?

Answered: 1 week ago