FACTS Assume that Tesla contracts to build a tram for its Nevada Gigafactory, which is expected to be completed in 17 months. The current-year payments
FACTS Assume that Tesla contracts to build a tram for its Nevada Gigafactory, which is expected to be completed in 17 months. The current-year payments to the contractor are $240,000 on March 1, $480,000 on July 1, and $360,000 on November 1. QUESTION How would you compute the weighted-average accumulated expenditures for months left. Tesla? I periods remaining