Question

1 Approved Answer

Ifthe indirect costs for each duration are $520 for 27 ueeks, $460 for 26 weeks, $400 for 25 weeks, $340 for 24 weeks, $280

image text in transcribedimage text in transcribed

Ifthe indirect costs for each duration are $520 for 27 ueeks, $460 for 26 weeks, $400 for 25 weeks, $340 for 24 weeks, $280 for 23 vseeks, and $240 for 22 weeks, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $30 for every week you shorten the project from your original planning network. Would you take it? If so, for how many weeks? (8+2+2=12 M) ACT. NORMAL NORMAL CASH A c T'ME to 6 cosr CRASH COST TIME go 50 too t 2 too

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Architecture Fundamentals And Principles Of Computer Design

Authors: Joseph D. Dumas II

2nd Edition

1032097337, 978-1032097336

Students also viewed these General Management questions