Question
Figure 7 Service Departments Producing Departments Personnel Maintenance Fabrication Assembly Budgeted overhead $80,000 $144,000 $280,000 $320,000 Machine hours 24,000 16,000 Number of employees -- --
Figure 7
Service Departments Producing Departments
Personnel Maintenance Fabrication Assembly
Budgeted overhead $80,000 $144,000 $280,000 $320,000
Machine hours 24,000 16,000
Number of employees -- -- 30 50
a. Personnel costs are allocated based on the number of employees, and maintenance costs are allocated based on machine hours.
30. Refer to Figure 7. The amount of Personnel costs allocated to the Maintenance Department using the direct method would be
a | $8,889 |
b | $0 |
c | $10,000 |
d | $8,163 |
e | none of the answers
b. Refer to Figure 7. The amount of Personnel costs allocated to the Fabrication Department using the direct method would be
d. Refer to Figure 7. Using the step method, allocate service department costs starting with personnel (assume the the maitenance department has 10 employees). The amount of Maintenance costs allocated to the Fabrication Department would be
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started