Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Final Exam ME 4 7 7 Date 1 0 / 0 2 / 2 0 2 4 Time allowed 2 . 0 0 hrs Q#
Final Exam ME Date Time allowed hrs
Q#
awhat is the project?
bwhat is the triple constraint of the project?
cwho are the key project stock holder?
dwho is the project manger?
why crashing the project?
Q# Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities
Activities H R T start the project.
Activity can start when Activities and are completed.
Activity Ealso depends on Activity R
Activity X follows Activity H and precedes Activity L
Activity E is preceded by Activities T and P
The predecessors to Activity G are Activities L T and P
The successors to Activity T are Activities E S W and D
Activity P cannot begin until Activity W is finished.
Activity P and F follow Activities W and D and precede Activities E and R
Activity depends on T and P and precedes Activity L
Q# Find the critical path find the slack value? Draw the Gantt chart.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started