Find the critical path. Find the normal duration time of the project. Find the cost associated with the normal duration time. Find the cost associated
Find the critical path.
Find the normal duration time of the project.
Find the cost associated with the normal duration time.
Find the cost associated with crashing for three days.
The table below shows data for a simple project. Activity Preceding Normal Normal Crash Crash activity duration cost duration cost A 2 _ 1 D 5 - 3 1 G F 2 500 1 1 000Step by Step Solution