Find the critical path(s) from the information in the table. Identify the critical path(s) and the number of days the critical path(s) is/are. Activity A
- Find the critical path(s) from the information in the table. Identify the critical path(s) and the number of days the critical path(s) is/are.
Activity | A | B | C | D | E | F | G | H | I |
Days | 3 | 4 | 5 | 6 | 6 | 5 | 3 | 4 | 3 |
Predecessor | - | A | A | A | B | B | D | C, F, G | E, H |
- What should a Project Manager if you find you have more than 1 critical path on your project. Support your discussion with a reference.